MEMO To: Rick Hartt From: Brett Mellor Date: September 7, 1994 Re: W2SZ Project Status The W2SZ building project is nearing completion. Yet to be completed are the installation of a gas line, paving the parking lot, demolition of the old building, and a few small items inside the building. This includes wiring the alarm, patching up the framework, some electrical details, etc. Although somewhat slow, W2SZ is still satisfied overall with the rate of completion. We understand the cuts that have been made in RPI shops. We have made an effort to transfer some of the work to the club to help in whatever marginal way. The majority of club equipment has already been moved into the new building. We should complete the move by this Tuesday, September 13, but possibly as early as Sunday. Anytime after then, the building will be ready for demolition. The method of which still needs to be discussed. An open house is tentatively scheduled for Alumni/Parents weekend. In the meantime, W2SZ will be busy customizing the building and rennovating our other facilities to prepare for the open house. -Brett Mellor N1LAG President, W2SZ ARC CC: R. Carney C. Fitzgerald